There are about 400 families in the ‘Classic Paradise’ layout at Begur road in Bengaluru. I was one of the first few residents to have moved here in 2003. There was no water back then days either, but in 2017, the government promised we would get water as it bought five zones (ours included) under the Bruhat Bengaluru Mahanagara Palike (BBMP). We were supposed to be supplied with water from the Cauvery river.
We became hopeful when the Bengaluru Water Supply and Sewerage Board (BWSSB) started laying pipelines in Begur two years ago, but to date, we haven’t received water.
In November 2018, when the BWSSB started the digging work, they made a mess of the roads here. As a fellow resident, Bharat says:
Residents began representing their grievances persistently to the departments concerned. Thankfully, the roads are in better shape now, but whether they will stay in such condition is an open-ended question.
This layout serves as a key link road connecting Hulimavu, Begur Road and Bommanahalli and Electronic City sides. Yet this is the condition.
Water has become so scarce and costly that we don’t throw away the used water from our washing machine or from washed clothes. We save each drop. Some residents have taken to rainwater harvesting.
I used to buy water for Rs 210 per tanker in 2003-04. Now, the cost of a water tanker has increased to Rs 700. These private suppliers prove heavy on our pockets.
Another resident, Roopa, faces the same problem.
Unfortunately, tankers are not readily available. The suppliers make excuses like ‘water is not available, we will come some other time’.
Water is essential. Without water, we can’t live. The BWSSB, having taken the deposit amount, is yet to connect Cauvery water pipelines to our homes. They have neglected us totally and are shifting deadlines without paying heed to the problems caused to citizens. The BWSSB had promised to give us water connection by July 2019.
Tushar Giri Nath, Chairperson of the BWSSB, spoke to The Quint and assured that the pipeline work would be completed within 10 to 15 days.
(All 'My Report' branded stories are submitted by citizen journalists to The Quint. Though The Quinti inquires into the claims/allegations from all parties before publishing, the report and the views expressed above are the citizen journalist's own. The Quint neither endorses, nor is responsible for the same.)
(At The Quint, we question everything. Play an active role in shaping our journalism by becoming a member today.)
Published: 17 Oct 2019,04:41 PM IST